What Should a Tolerance Report Include for Injection Molded and Machined Parts?
Need a Project-Specific Answer?
Have a question about plastic components, injection molding or production requirements?
Talk With Our Manufacturing Team
Share the part, material, quantity or production detail behind your question so our team can discuss the practical manufacturing considerations.
I’m a procurement engineer at a mid-sized hardware brand. We are currently sourcing a new injection-molded bracket with pressed-in hardware inserts for a power tool accessory line.
The supplier has submitted a tolerance report from the T1 sample run, covering about 35 dimensional checks. Most measurements are within the drawing limits, but there are three borderline dimensions sitting right at the upper or lower limit, and one hole-to-hole center distance is 0.08 mm out of spec.
The supplier says these are “acceptable for function” because the bracket locates into a larger housing with clearance and the hole distance will not affect assembly.
Our own design team is not fully convinced, and I have to decide whether to accept the report, ask for tooling correction, or request more measurement data before we release the next stage. I’m also not sure if a tolerance report from T1 samples is enough to judge production stability.
What should I check first in this tolerance report, and how should I decide whether the out-of-spec condition is a real risk or just a paperwork issue?
Expert Answer
Manufacturing team members may answer the same sourcing question from different practical perspectives. The accepted answer is marked for quick reference.
The first issue is not whether the supplier believes the part is acceptable, but whether the tolerance report is reliable enough to support a tooling approval decision. A T1 measurement report from a small sample set can show a part that fits today but still hide a production process that will drift outside tolerance later. The borderline dimensions and the 0.08 mm hole-to-hole deviation should therefore be treated as separate types of risk.
Start by checking the report itself. Confirm the drawing revision, material grade, mold number, cavity number, sample size, measurement equipment, and date. If the bracket is produced in a multi-cavity tool, the report should show cavity-specific results. Mixed cavity data can make an out-of-spec condition look like one problem when it is actually limited to a single cavity. Also confirm that all dimensions required by the drawing were measured. An incomplete report that skips difficult datum features or hidden dimensions is not a valid basis for approval.
Next, classify the dimensions by function. A hole-to-hole center distance is usually an interface dimension. It should not be accepted based only on the supplier’s statement that the bracket locates into a larger housing with clearance. Request the assembly stack calculation or a physical fit test with actual mating parts at the maximum material condition. The 0.08 mm deviation may be harmless if the clearance remains positive under worst-case stack-up, or it may cause fastener bind, insert stress, or alignment drift. If the supplier has not performed that check, the part cannot be dispositioned as “functional.”
For the three borderline values sitting at the upper or lower limit, evaluate the process center. A dimension that is just inside the limit on a T1 sample can easily go out of tolerance during normal production because of lot-to-lot material variation, mold temperature change, or tool wear. Ask the supplier to run a 30-piece pilot batch under production-representative parameters and calculate capability for those dimensions. If the process is stable but centered near the limit, a process adjustment may be enough. If the spread itself is too wide, the process is not capable and the tool or part design may need correction.
Measurement correlation should be resolved before any decision. Confirm that the supplier used the same datum scheme and fixture concept shown on the drawing. A CMM best-fit alignment can produce different results from a hard gauge or functional fixture. Ask how the part was restrained during measurement, and whether the pins, bosses, or inserts were installed before checking. If your incoming inspection measures the same samples differently, that difference must be resolved first. Otherwise, the report is just one supplier’s measurement opinion rather than an agreed quality record.
For the out-of-spec dimension, the decision should be one of three formal actions: reject and request tool correction, accept with a documented engineering deviation, or request a remeasurement and capability study before making a decision. A verbal statement that the part is “acceptable for function” is not enough. If the hole center distance is truly non-functional because of generous assembly clearance, the proper response is to update the drawing or issue a written concession with the affected lot, date, and quantity. That prevents the same issue from being treated as a defect in future receiving inspection.
For prevention, agree on the inspection protocol before tooling start. Define the critical dimensions, the measurement method, the sample size, and the expected capability requirement. For this bracket, the hole-to-hole center distance and insert location should be identified as critical-to-function features. The supplier should include them in every dimensional report with individual values, not just pass/fail results. Request a full dimensional layout at T1, a short-run capability study before pilot approval, and ongoing Cpk or Ppk monitoring for those key features during mass production.
Finally, separate the tooling correction decision from the product function decision. Tooling may need correction because the process is not centered or because the feature is drifting, even if the current sample fits. A tolerance report should not answer the question “Does this part work?” by itself. It should answer a narrower question: “Did the produced part meet the agreed drawing and process control requirements?” If the answer is no, the acceptance decision needs engineering review, written disposition, and a defined follow-up validation.
On a T1 molded bracket, the first distinction to make is whether the measured values come from one cavity or multiple cavities. A tolerance report that mixes cavity data can hide offset between cavities, especially for a hole-to-hole center distance.
Request a cavity-by-cavity layout for the cavities producing this bracket. If the out-of-spec condition appears only in one cavity, the issue is likely core shift, uneven fill pressure, or a gate balance problem rather than an overall drawing mistake.
Check whether the hole positions are formed directly by the mold or produced by a secondary operation. If the holes are formed by pins or slides, wear on the pin retainer, insufficient shutoff, or movement during ejection can create position error.
The correction may require adjusting the core pin location, adding a more rigid support, or relocating the gate to balance fill. If the feature is machined after molding, the mold may still be acceptable and the fixture can be corrected separately.
Ask for a short closed-loop run after any tool change, not just a remeasured set of the same samples. That helps confirm the correction is stable under normal molding conditions.
Before deciding whether 0.08 mm is acceptable, the drawing should be checked for how the hole-to-hole dimension is toleranced and how the datum scheme is defined.
A tight true position or center distance with an unrealistic datum reference can make a molded part appear out of spec even when the functional fit is acceptable. If the drawing uses a loose ordinate dimension but the report measures from a different datum plane, the comparison may not be valid.
For a glass-filled nylon bracket, wall thickness changes around bosses, ribs, and the insert area can drive differential shrinkage. Borderline dimensions at the limit often indicate that the part is being molded at the edge of the process window, not necessarily that the steel is wrong.
Check the gate location, filling pattern, and packing time before requesting a tooling correction. A process-only trial may bring the three borderline dimensions back to center.
The out-of-spec hole distance deserves a dedicated DFM review. If the tolerance stack between the bracket hole and the mating housing has sufficient clearance, an engineering change may be more cost-effective than moving a core pin.
But that should be supported by a documented gap study, not by the supplier’s verbal judgment.
Functional approval should not come from the tolerance report alone. The bracket should be assembled with actual mating housings, fasteners, and inserts at the same condition that will be used in production.
The reported 0.08 mm center-distance deviation may disappear in the assembly clearance or it may create a screw bind, insert stress, or alignment issue. Only a physical fit check can confirm which one occurs.
Request samples from both the low and high sides of the dimensional range, not only nominal parts. If the supplier can provide off-tool samples that are purposefully selected near the tolerance extremes, the assembly team can check whether the clearance remains acceptable.
For a power tool accessory, vibration, repeated mounting, and removal should also be considered. A part that fits on the bench may shift under load if the hole location is already off nominal.
Also clarify whether the insert is installed before or after measurement. Pressing an insert can change the local material and distort the hole position.
The tolerance report should state the insert installation condition; otherwise the dimensional comparison may not reflect the final part the customer will assemble.
For hole-to-hole positions, the measurement method matters as much as the measured value. If the supplier used a vision system or CMM with a best-fit alignment, the reported deviation may be different from a hard fixture check.
Ask for the alignment method and datum simulation. The report should show how the part was constrained during measurement. A part that is not seated on the same datums as the production fixture can show exaggerated position error.
Secondary machining of holes after molding gives more control than a molded-in hole position. If the holes are drilled or reamed in a fixture, a 0.08 mm center-distance shift is normally correctable through fixture adjustment or bushing position.
The decision should then be whether the steel pin location can be adjusted, whether the hole is opened later, or whether the machining fixture can compensate.
Before rejecting the tool, ask for a repeat measurement of the same sample set and a separate measurement on a new sample run. This helps separate fixture error from process drift.
For borderline dimensions, a measurement uncertainty estimate of 0.02 to 0.04 mm can mean the difference between accept and reject.
The supplier should not state that a dimension is functionally acceptable without supporting evidence. The first step is to classify each reported dimension as critical, major, or minor.
A hole-to-hole center distance that affects fastener alignment is a major characteristic until proven otherwise. Borderline values on non-critical appearance dimensions can be dispositioned more easily, but interface dimensions should require formal approval from engineering and quality.
Check whether the tolerance report includes the number of samples, mold cavity, material lot, and inspection date. A T1 report with only three or five parts is not enough to judge production variation. Request a 30-piece capability study for the three borderline dimensions and the out-of-spec hole distance.
If the individual values are all near the tolerance edge but stable, the process may simply be centered wrong and can be corrected. If the values are widely spread across the tolerance band, the process itself may not be capable.
Insist on a documented measurement system correlation between the supplier and your incoming inspection. If your own team measures a different result on the same samples, that difference must be resolved before any acceptance decision.
The tolerance report should be evaluated as part of the complete assembly stack, not in isolation. For the hole-to-hole center distance, map the related features on the mating housing, the screw body diameter, the clearance hole, and the insert location.
Calculate the remaining gap under worst-case conditions using the lowest and highest reported values. If the assembly still has positive clearance, the deviation may be conditionally acceptable. If the calculation shows the screw can contact the hole edge or the insert can be forced outward, the part should not be released.
Borderline dimensions at the upper and lower limits can also indicate that the process output is not centered. Even if the sample fits, a later shift of 0.03 to 0.05 mm could create an interference.
The assembly risk is not only the current sample; it is the potential distribution during a full production run. Request lower and upper process data for the critical interface features rather than a single measurement set.
If the bracket has slotted holes or float, the tolerance may be unnecessarily tight. If the design cannot be changed, ask for 100% checking on the hole center distance during the first production batches until the process demonstrates stability.
A T1 tolerance report is a snapshot of one machine setup, often produced at slower cycle time and with more manual adjustment than normal production. The measured values may not represent steady-state output.
Before accepting the bracket, ask the supplier to run a pilot batch under standard cycle time, full mold temperature, and automatic operation. Then measure the same dimensions again.
The borderline dimensions are a warning sign for process centering. On a molded part, holding pressure, cooling time, and mold temperature can shift dimensions by several hundredths of a millimeter.
The supplier may be able to adjust the process to bring those dimensions back within the tolerance band without changing the tool. The out-of-spec hole distance, however, is less likely to be corrected by process alone if it is related to core location or uneven shrinkage.
Request the process parameter sheet used for the samples and the planned production parameters.
If the sample report was produced with parameters that cannot be sustained at cycle time or cost, the dimensional result is not a reliable basis for approval. The decision should be tied to production-representative output, not to hand-selected T1 parts.
In a multi-feature plastic bracket, hole-to-hole location error often points to asymmetric filling or differential shrinkage around the gate. Review the mold layout and gate position.
If the gate is located at one end, the material orientation and packing may be different between the two hole areas. This can create a repeatable shift even though the steel dimensions are correct.
The three borderline dimensions at the tolerance limit should be reviewed for whether the tolerance was applied uniformly across a large molded area. Flatness-related dimensions and hole positions on a ribbed wall can be influenced by cooling, ejection, and warpage.
A tooling change may not solve the issue if the root cause is the part geometry or the processing window. In that case, the better correction may be a drawing change that reflects the achievable process capability.
For the 0.08 mm hole center distance, ask the supplier to check core pin deflection during injection. If the pins are long and unsupported, they can shift under plastic pressure. Adding a locating support or changing pin diameter can improve repeatability without a complete tool rebuild.
The material itself can explain a large part of dimensional variation in a glass-filled nylon bracket. Fiber orientation, moisture content, and lot-to-lot viscosity changes affect shrinkage differently in the flow and cross-flow directions.
If the tolerance report is based on dry-as-molded samples, the dimensions may change again after moisture conditioning. Confirm whether the parts were measured dry or conditioned, and request measurements at the same moisture state the customer will receive.
For a hole-to-hole center distance, differential shrinkage between two boss areas can easily exceed 0.05 to 0.10 mm if the fiber orientation is not balanced.
The supplier should check whether filling is even and whether the material lot used for T1 matches the approved grade. A different lot with higher glass content or different viscosity should not be substituted without a new dimensional validation.
Ask for the material certificate and shrinkage data for the actual lot. If the out-of-spec condition is material-related, a process adjustment or gate change may bring the dimension back into tolerance.
If the tolerance is too tight for the selected grade, a material or drawing change should be considered before committing to tooling correction.
Tip: The clearest questions usually include the part information, application, production quantity and the specific requirement that needs an expert answer. More complete context helps the manufacturing team give a more useful response.